Configuring Present settings
This guide explains how to configure some advanced settings for the Present page.
Prerequisites
In Explore & Present, you need Workspace Admin (WA) permissions to change the settings explained in this guide. For more information, see Roles and permissions in Explore & Present.
Configuring color mapping
A color mapping assigns a color to a specific dimension value. The assigned color is used for the selected dimension value whenever it appears in a visualization.
For example, if you assign a bright red color to the value Campaign A, and create a bar chart visualization showing the number of clicks for different campaigns, the bar representing the clicks value for Campaign A will be the selected bright red color. All dimensions will be checked for the values configured in the color mapping.
To create and configure color mappings, follow these steps:
-
Go to the Present page.
-
In the top left corner, click Select workspace, then Administration.
-
In the Present section of the administration menu, click Colors.
-
To add a new color mapping, follow these steps:
-
Click + Add value.
-
In Color, select the color you want to assign. You can select a color on the color map, or enter the HEX or RGB values for a color.
-
In Dimension value, enter the value that you want to be displayed in the selected color.
-
Click Save.
-
-
To edit an existing color mapping, click the selected color to choose a new color, or click the dimension value to change the dimension value to which the color is assigned.
-
To delete an existing color mapping, click Delete in the row for the color mapping, then click Save.
As a result, you have configured color mapping for the selected dimension value.
Configuring chart events
A chart event is a line that is displayed at a specific time on a visualization that shows data over time. For example, you could create a chart event to mark the start of a new advertising campaign on a visualization that shows your cost per click metric over the past 6 months, or create a chart event to mark a website outage in order to explain any anomalies in your data.
To create and configure chart events, follow these steps:
-
Go to the Present page.
-
In the top left corner, click Select workspace, then Administration.
-
In the Present section of the administration menu, click Chart events.
-
To add a new chart event, follow these steps:
-
In the top right corner, click + Create chart event.
-
In Timestamp, select the time and date at which the chart event will appear in visualizations.
-
In Description, enter a description of the chart event.
-
In Category, select the category to which the chart event belongs.
-
(Optional) Select the Inherit checkbox to make this chart event visible in all child workspaces of your current workspace.
-
Click Create.
-
To go back to the list of chart events, in the top right corner, click Chart event list.
-
-
To edit or delete an existing chart event, in the row for the corresponding chart event, click Edit, then perform any of the following actions:
-
To edit the chart event, change the chart event settings and click Update.
-
To delete the chart event, click Delete and then, in the confirmation dialog, click Delete chart event.
-
As a result, you have configured a chart event, and can now add this chart event to visualizations in the Explore page. For more information, see Adding chart events to a visualization.